SINAMICS DCM
Engineering information
Dynamic overload capability
5/3
Siemens D 23.1 · 2014
5
■
Overview
(continued)
Basic task 1
• Given:
Unit, cycle duration, overload factor, overload duration
•
To be found:
(Min.) base-load duration and max. base-load current
• Solution:
Example for basic task 1
• Given:
- Unit with 30 A
- Cycle duration 113.2 s
- Overload factor 1.45
- Overload duration 20 s
•
To be found:
- (Min.) base-load duration
- Max. base-load current
• Solution:
- Limiting characteristic for a unit with 30 A
- Overload factor 1.5
- Overload duration
300
= 300 s/113.2 s
×
20 s = 53 s
→
- Max. base-load current = 44 %
I
rated
= 13.2 A
Basic task 2
• Given:
Unit, cycle duration, overload factor, base-load current
•
To be found:
Maximum overload duration, minimum base-load duration
• Solution:
Example for basic task 2
• Given:
- Unit with 30 A
- Cycle duration 140 s
- Overload factor 1.15
- Base-load current = 0.6
×
I
rated
= 18 A
•
To be found:
- Maximum overload duration
- Minimum base-load duration
• Solution:
- Limiting characteristic for a unit with 30 A
- Overload factor 1.2
- Base-load current = 60 %
I
rated
→
- Overload duration
300
= 127 s
- Max. overload duration = 140 s/300 s
×
127 s = 59 s
- Min. base-load duration = 140 s - 59 s = 81 s
Explanation of terms:
Base-load duration
300
= min. base-load duration for 300 s
cycle duration (300 s
–
overload duration)
Overload duration
300
= max. overload duration for 300 s cycle
duration
Cycle duration
< 300 s
≥
300 s
1. Determine the characteristic
Select the limiting characteristic for the specific unit and the specific overload factor
2. Overload duration
300
=
300 s/cycle duration
×
overload duration
Overload duration
300
3. Base-load duration
300
=
300 s – overload duration
300
4. Base-load duration
300
< base-load
duration
300
for max. base-load current = 0
Yes
: Required duty cycle cannot be configured
No
: Read the max. base-load current for overload duration
300
from the limiting characteristic
5. Determine the percentage for the base-load
current
Read the percentage for the base-load currents from the diagram
Cycle duration
< 300 s
≥
300 s
1. Determine the characteristic
Select the limiting characteristic for the specific unit and the specific overload factor
2. Max. overload duration =
(Cycle duration/300 s)
×
overload duration
300
300 s – base-load duration
300
3. Min. base-load duration =
Cycle duration – max. overload duration
Cycle duration – max. overload duration
© Siemens AG 2014
1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12 - 13 - 14 - 15 - 16 - 17 - 18 - 19 - 20 - 21 - 22 - 23 - 24 - 25 - 26 - 27 - 28 - 29 - 30 - 31 - 32 - 33 - 34 - 35 - 36 - 37 - 38 - 39 - 40 - 41 - 42 - 43 - 44 - 45 - 46 - 47 - 48 - 49 - 50 - 51 - 52 - 53 - 54 - 55 - 56 - 57 - 58 - 59 - 60 - 61 - 62 - 63 - 64 - 65 - 66 - 67 - 68 - 69 - 70 - 71 - 72 - 73 - 74 - 75 - 76 - 77 - 78 - 79 - 80 - 81 - 82 - 83 - 84 - 85 - 86 - 87 - 88 - 89 - 90 - 91 - 92 - 93 - 94 - 95 - 96 - 97 - 98 - 99 - 100 - 101 - 102 - 103 - 104 - 105 - 106 - 107 - 108 - 109 - 110 - 111 - 112 - 113 - 114 - 115 - 116 - 117 - 118 - 119 - 120 - 121 - 122 - 123 - 124 - 125 - 126 - 127 - 128 - 129 - 130 - 131 - 132 - 133 - 134 - 135 - 136 - 137 - 138 - 139 - 140 - 141 - 142 - 143 - 144 - 145 - 146 - 147 - 148 - 149 - 150 - 151 - 152 - 153 - 154 - 155 - 156 - 157 - 158 - 159 - 160 - 161 - 162 - 163 - 164 - 165 - 166 - 167 - 168 - 169 - 170 - 171 - 172 - 173 - 174 - 175 - 176 - 177 - 178 - 179 - 180 - 181 - 182 - 183

Ask for a free quotation – We are at your disposal

Call us at +39 080.5367090 or send an email to info@tecnicaindustriale.com